CONSTRUCTION UPDATE

Last Updated: 16th May, 2019

On behalf of Villawood Properties, we would like to provide you with a construction update for our Rathdowne community.

Stage 1, Carmichael Release
STATEMENT OF COMPLIANCE OBTAINED. We are happy to announce that we have passed all Authority audits and have obtained our Statement of Compliance from Council. We will proceed to title lodgement and our solicitors will individually notify all Stage 1 purchasers upon Title Registration. If you haven’t already, we recommend contacting your legal representative and lender to ensure all preparations are made ahead of settlement.

Stage 2, Carmichael Release
NEARING PRACTICAL COMPLETION. We have begun formal testing on all sewer and water infrastructure having recently completed pre-testing. Final layers of road pavement are currently being constructed along with lot grading and topsoiling. We will individually contact all purchasers (purchaser Solicitor) as we progress closer to Practical Completion and obtaining our Statement of Compliance for Stage 2. If you haven’t already, we recommend contacting your legal representative and lender to ensure all preparations are made ahead of settlement.

Stage 3, Lavelle Release
NEARING PRACTICAL COMPLETION. We have begun formal testing on all sewer and water infrastructure having recently completed pre-testing. Final layers of road pavement are currently being constructed along with lot grading and topsoiling. We will individually contact all purchasers (purchaser Solicitor) as we progress closer to Practical Completion and obtaining our Statement of Compliance for Stage 2. If you haven’t already, we recommend contacting your legal representative and lender to ensure all preparations are made ahead of settlement.

Stage 4, Portofino Release
Bulk earthworks are complete along with all sewer and drainage infrastructure. Road boxing is now complete with construction of water and gas infrastructure now underway. Construction of the road subgrade has also commenced. The anticipated title delivery date remains unchanged at November 2019.

Stage 5, Providence Release
CONSTRUCTION COMMENCED. Stripping and early earthworks are now underway with sewer construction following this in mid-late June.

Anticipated Title Timeframes:
Stage 1 – May 2019
Stage 2 – June 2019
Stage 3 – June/July 2019
Stage 4 – November 2019
Stage 5 – July/August 2020