CONSTRUCTION UPDATE

Last Updated: 17th January, 2019

On behalf of Villawood Properties, we would like to provide you with a construction update for our Rathdowne community.

Welcome to the first Construction Update of 2019; and what a year it’ll be! With title registration imminent, particularly for Stages 1 and 2, we encourage you to prepare for settlement and to contact your solicitor/lender to ensure you are ready for settlement once titles are received.

Stage 1, Carmichael Release
Stage 1 is really starting to take shape with all roads, kerbs and underground infrastructure now constructed. Electrical and communication cables have also been installed with footpath and vehicle crossover construction now underway with top-soiling and final lot grading to follow. We look to deliver titles in February 2019.

Stage 2, Carmichael Release
Bulk earthworks, critical sewer lines and stormwater drainage are complete along with underground water and gas infrastructure. Subgrade pavement layers have been constructed with kerb and channel construction underway. Electrical and communication cables will be installed followed by construction of the concrete footpaths and vehicle crossovers. The anticipated title delivery date remains unchanged at March 2019.

Stage 3, Lavelle Release
Bulk earthworks, critical sewer lines and stormwater drainage are complete. Water and gas infrastructure is complete and road construction is underway. The anticipated title delivery date remains unchanged at April 2019.

Stage 4, Portofino Release
Site stripping and bulk earthworks is complete. Sewer construction has commenced, and drainage construction is due to start over the coming week. The anticipated title delivery date remains unchanged at November 2019.

Stage 5, Providence Release
Detailed engineering is with Council for review. Anticipated construction commencement is February 2019 pending engineering approval.

Anticipated Title Timeframes:
Stage 1 – February 2019
Stage 2 – March 2019
Stage 3 – April 2019
Stage 4 – November 2019

View the latest Rathdowne site images here: