CONSTRUCTION UPDATE

Last Updated: 8th March, 2019

On behalf of Villawood Properties, we would like to provide you with a construction update for our Rathdowne community.

Stage 1, Carmichael Release
NEARING PRACTICAL COMPLETION: With all roads and infrastructure now in place we have begun undertaking final site inspections and obtaining approval from the relevant authorities. Water and sewer testing is complete and telecommunications consent has been obtained.

We are coordinating with Council and the electrical authority to undertake their respective final audits over the coming weeks with Statement of Compliance to be issued thereafter. We anticipate title lodgement in late March with settlements forecast for April. If you haven’t already, we recommend getting in touch with your lender and conveyancer to ensure a timely settlement once Title Registrations have occurred.

Stage 2, Carmichael Release
Bulk earthworks, critical sewer lines and stormwater drainage are complete along with underground water and gas infrastructure. Kerb and channel construction is complete with electrical and telecommunications trenching now underway. Concrete footpaths and crossover construction will commence over the coming week.

We have experienced delays in construction over the past month due Council hold-point inspections and minor redesign requirements. These have now been resolved and we anticipate construction to be complete in late April/early May with Title registration shortly after.

Stage 3, Lavelle Release
Bulk earthworks, critical sewer lines and stormwater drainage are complete along with underground water and gas infrastructure. Kerb and channel construction is complete with electrical and telecommunications trenching now underway. Concrete footpaths and crossover construction will commence over the coming week.

We have experienced delays in construction over the past month due Council hold-point inspections and minor redesign requirements. These have now been resolved and we anticipate construction to be complete in late April/early May with Title registration shortly after.

Stage 4, Portofino Release
Bulk earthworks are complete with both sewer and drainage construction nearing completion. Road boxing is to commence over the coming weeks once the final sewer and drainage lines have been constructed. The anticipated title delivery date remains unchanged at November 2019.

Stage 5, Providence Release
Final Council comments received with early earthworks to commence over the coming weeks.

Anticipated Title Timeframes:
Stage 1 – March/April 2019
Stage 2 – May/June 2019
Stage 3 – May/June 2019
Stage 4 – November 2019