Select your stage to track construction and title progress:
| 100% Complete | |
| 100% Complete | |
| 100% Complete | |
| 100% Complete | |
| 90% Complete | |
| 50% Complete | |
| 15% Complete |
Stage 32
Work on the stage are now complete, and we have commenced the compliance phase with the authorities.
We are currently anticipating titles to be issued in late September 2026.
Stage 21
Due to national supply shortages of high-voltage (HV) electrical materials, we have experienced delays to the construction program. As the HV infrastructure needs to be installed before further works can progress, this has unfortunately resulted in an approximately two-month delay.
Our team has been working closely with our contractors and suppliers behind the scenes, and we are pleased to confirm that the required materials have now been secured and works can progress.
Based on the revised construction program, we are anticipating Statement of Compliance in late December 2026. With Council and industry closures over the Christmas period, we expect titles to be issued in late-Jan to early-Feb 2027.
We appreciate your patience and understanding. Please be assured that our team and construction crews are working hard to progress the stage and deliver titles as soon as possible.
Stage 22
The planning permit and engineering plans have now been approved, with initial earthworks scheduled to commence in late September 2026.
Based on the current construction program, we are anticipating titles to be issued in June 2027.