Once the Planning Permit has been issued by Council, stage specific plans, including roads and drainage, sewer and water, gas, electrical, telecommunication and landscaping plans, are lodged for approval with the relevant authorities.
Winslow Constructors have mobilised on site with site stripping and bulk earthworks complete. Sewer and drainage installation has also been completed. Water and gas service installation is now complete. Road construction including kerb and channel now complete with concrete works underway. Final topsoil and compliance auditing will be completed over the coming weeks. Titles are anticipated in September 2022.