Once the Planning Permit has been issued by Council, stage specific plans, including roads and drainage, sewer and water, gas, electrical, telecommunication and landscaping plans, are lodged for approval with the relevant authorities.
Early earthworks commenced in July and since sewer has been completed, with drainage well underway. Water and electrical will commence in the coming weeks. Settlements are anticipated for late Q2 2025.