Facebook Facebook Instagram Twitter YouTube Linked In Linked In Email Phone Phone Next Scroll to move Touch to move edit edit Play Play Pause Volume Mute Zoom Search Map Map List Social New Application Document Request User Lot Area Frontage Depth Bedrooms Bathrooms Garage Price Range Download Location Location Filter Bedrooms Bathrooms Bathrooms Lot Size Stage Sales Sales Titled Lot Lot Club Access

Redstone Construction Updates:

November 2020

Stage 1

Future residents will be pleased to know watermain installation is complete. Roadworks are in full swing with the first kerb recently installed, and over the next month we’ll start to see the first layers of asphalt. Titles are on track for the second quarter of 2021.

Stage 2

Sewer, drainage and watermain works are complete, and the roads have started to take shape with preparations being made to the base layers. Titles are on track for the second quarter of 2021.

Stage 3

We’re happy to announce construction of Stage 3 has commenced! Earthworks are currently in progress and titles are expected in the fourth quarter of 2021.

October 2020:

Construction is full steam ahead at Redstone with progress on track and in line with program.

Stage 1

Sewer and drainage works are complete. Installation of water and gas is underway. In the coming month we’ll start to see the various road forms taking shape with preparation of the road’s subgrade. Titles are forecast for Q2 2021.

Stage 2

Sewer and drainage works are progressing well. In the coming month we’ll see installation of water and gas. Titles are forecast for Q2 2021.

 