Choose your stage number below to track the construction and title progress of your lot.
72% Complete | |
100% Complete | |
70% Complete | |
72% Complete | |
8% Complete | |
6% Complete |
Shepherds Lane Wetland – detailed design has been submitted to Melbourne Water for approval. Interim works have recently been completed to accommodate current stages.
Turnberry Wetland – detailed design has been submitted to Melbourne Water for approval.
Sewer Pump Station – Civil works are mostly complete with electrical works underway. Completion is forecast for Q3 2025.
Stages 1 – 11 – Titled
Stage 21A – June 2025
Stage 16 – June 2025
Entry works and internal connection roads June 2025
Earthworks nearing completion.