Facebook Facebook Instagram Twitter YouTube Linked In Linked In Email Phone Phone Next Scroll to move Touch to move edit edit Play Play Pause Volume Mute Zoom Search Map Map List Social New Application Document Request User Lot Area Frontage Depth Bedrooms Bathrooms Garage Price Range Download Location Location Filter Bedrooms Bathrooms Bathrooms Lot Size Stage Sales Sales Lot Club Access

 

CONSTRUCTION UPDATE – 4 December 2019

ARMSTRONG

Stage 42

Kerb and channel, electrical and telecommunications were completed in November. Footpath and vehicle crossover construction has commenced. Stage 42 is programmed for completion in late February 2020, after which titles be available in late March / early April 2020. Site conditions in Stage 42 can be viewed here:  http://www.cloud9.camera/armstrong2.

Stage 40A (Lots 4017 to 4033, Lots 4049 to 4052)

Construction works will be completed by mid-December. Compliance audits will bridge the Xmas/New Year break, and be completed in January 2020. Titles will be available in February 2020.

Stage 40 (Lots 4001 to 4013 and Lots 4034 to 4042)

The stabilisation of Boundary Road subgrade was completed in October. However testing of the subgrade after stabilisation was only partially successful. Further stabilisation was successfully completed in November, but causing kerb and channel construction to be re-scheduled from December 2019 to early 2020. Current title forecast is now June 2020 after completion of works in late April 2020.

Stage 40B Lots 4043 to 4048, and Lots 4013 to 4016

Construction is in conjunction with Stage 40. Title forecast is June 2020 after completion of works in late April 2020.

Stage 44

Road base stabilisation and capping was completed late November. Kerb and channel will now commence in mid-December. Completion of the subdivision is now programmed for May 2020, due to delays arising from the road base stabilisation. Titles are expected the following month, June 2020.

Stage 45

Sewer, drainage and road excavation have been completed. Water and gas installation will be completed this month. Construction is currently programmed to be completed in June 2020 with Titles available in August 2020.

Stage 48

Road subgrade stabilisation was completed in October and covered in November. Due to the time taken to rectify road subgrade, scheduling of kerb and channel has been put back to January 2020. Completion of the subdivision is now programmed for early April 2020. Titles are currently forecast for June 2020.

Stage 63 and Stage 64

Front-of-lot footpath works and service connections are nearing completion. Compliance audits will be completed in January 2020, with titles expected in February 2020.

Stage 43

Bulk Earthworks will be completed this week. Sewer reticulation works have commenced. Works are scheduled to be completed in August 2020. Titles remain forecast to be available in the December quarter of 2020.

SANCTUARY

Stage 6A

Kerb and channel has been completed. Electrical reticulation will be completed in December 2019. Completion of the stage is forecast for February 2020 with titles expected the following month, March 2020.

Stage 6B

Construction commenced in November. Titles are expected early in the September quarter of 2020.

Loading...
Loading...
Loading...
Loading...