Facebook Facebook Instagram Twitter YouTube Linked In Linked In Email Phone Phone Next Scroll to move Touch to move edit edit Play Play Pause Volume Mute Zoom Search Map Map List Social New Application Document Request User Lot Area Frontage Depth Bedrooms Bathrooms Garage Price Range Download Location Location Filter Bedrooms Bathrooms Bathrooms Lot Size Stage Sales Sales Lot

 

CONSTRUCTION UPDATE – 4 October 2019

ARMSTRONG

Stage 42

Road stabilisation has been completed. Installation of kerb and channel will commence next week, followed by electrical installation and footpaths in November. Stage 42 is currently programmed for completion in February 2020, after which titles will be available in March 2020.. Site conditions in Stage 42 can be viewed here:  http://www.cloud9.camera/armstrong2.

Stage 40A (Lots 4017 to 4033, Lots 4049 to 4051)

Kerb and channel installation has been completed.  Electrical installation will be completed in October. Completion of the subdivision is currently programmed for December 2019, with Titles available in February 2020.

Stage 40 (Lots 4001 to 4013 and Lots 4034 to 4042)

Drainage, sewer, and water reticulation have been completed. Boundary Road subgrade conditions have continued to present problems until the end of winter. A stabilisation specification has now been confirmed. The onset of warm dry weather will allow stabilisation to be completed by mid-October. Kerb and channel is programmed for completion in mid-December. Title forecast is now May 2020 after completion of works in late March / early April.

Stage 40B Lots 4043 to 4048, and Lots 4013 to 4016

Construction is in conjunction with Stage 40. Title forecast is now May 2020 after completion of works in late March / early April.

Stage 44

Sewer and Drainage have been completed. Water and gas are currently being installed. Significant unsuitable road subgrade conditions have affected program and title dates. Road stabilisation will be completed in October, with kerb and channel to be laid early December. Completion of the subdivision is currently programmed for April 2020, with Titles available in late May 2020. Site conditions can be viewed here: http://www.cloud9.camera/armstrong3

Stage 45

Sewer installation is completed. Drainage installation is in progress. Construction is currently programmed to be completed in June 2020 with Titles available in August 2020.

Stage 48

Sewer, drainage, water and gas reticulation have been completed. Road stabilisation will be completed in October followed by kerb and channel in November. Titles forecast continues to be June quarter of 2020.

Stage 63 and Stage 64

Construction will commence this month. Titles are expected in February 2020.

Stage 43

Construction will commence in late October 2019. Titles are forecast to be available in the December quarter of 2020.

Main Image

SANCTUARY

Stage 6A

Sewer, drainage and water have been completed. Road stabilisation has been required and will be completed in the next two weeks. Kerb and channel will commence late October. Titles for Stage 6A are expected in the March quarter of 2020.

Stage 6B

Construction will commence in late October. Titles are expected early in the September quarter of 2020.

Loading...
Loading...
Loading...
Loading...