fbpx
Villawood Properties Facebook Facebook Instagram Twitter YouTube Linked In Linked In Email Phone Phone Next Scroll to move Touch to move edit edit Play Play Pause Volume Mute Zoom Search Map Map List Social New Application Document Request User Lot Area Frontage Depth Bedrooms Bathrooms Garage Price Range Download Location Location Filter Bedrooms Bathrooms Bathrooms Lot Size Stage Sales Sales Titled Lot Lot Club Access Visitors Virtual Tour Open Close

Construction Update

Stage 5 | Titles Expected Aug 2024     

Valuations: Jul 24   |   Estimated Access For Soil Testing: Jul 24   |   Site Survey: Aug 24   |   Estimated Title Dates: Aug 24   |   Settlements Commencement: Sep 24

27%
Overall Progress
Loading
100%
Phase 1

Planning & Engineering Approvals

Detailed engineering design is under review with authorities. Site works are expected to start in November 2023

  • Stage 3 - Phase 1
80%
Phase 2

Earthworks

Works are progressing well, earthworks are complete and some underground services have been installed. The sales team will be in touch when site visit dates for valuations are confirmed.

  • May Update
Tip: Start your journey with a Villawood Builder Partner and find your future home
10%
Phase 3

Sewerage, Drainage, Water & Gas Reticulation

Works are progressing well, earthworks are complete and some underground services have been installed. The sales team will be in touch when site visit dates for valuations are confirmed.

  • Stage 3 - Phase 3
0%
Phase 4

Road Base, Kerbs, Electrical & Fibre

Further underground services are installed including electricity and telecommunications (fibre internet). Road construction takes place over several phases. Excavation and preparation of the base layer commences first and is often followed by installation of various conduit crossings and kerb construction.

0%
Phase 5

Footpaths, Road Pavement & Asphalting

Construction of the road continues, with numerous road layers completed through to the final asphalt layer. The stage starts to look like your future community, with driveways, footpaths and nature strips created.

0%
Phase 6

Completions & Inspections

Each stage is closely inspected and audited by various authorities to ensure the new infrastructure complies with the plans and relevant standards. The inspections and audits can be quite complex and often take some time to complete. Once all authorities have provided their approvals, Council will issue a Statement of Compliance (SoC).

0%
Phase 7

Titles and Settlements

Lodgement packages are prepared and finalised, individual titles for each lot are issued by the Titles Office. Your solicitor or finance broker is notified when this has occurred and will arrange for settlement.
Once settlement has occurred, your land is ready for you to commence the construction of your new home!

Tip: This is when the land will become available for inspections for valuations and builder assesment
Loading...
Loading...
Loading...
Loading...
Loading...