fbpx
Villawood Properties Facebook Facebook Instagram Twitter YouTube Linked In Linked In Email Phone Phone Next Scroll to move Touch to move edit edit Play Play Pause Volume Mute Zoom Search Map Map List Social New Application Document Request User Lot Area Frontage Depth Bedrooms Bathrooms Garage Price Range Download Location Location Filter Bedrooms Bathrooms Bathrooms Lot Size Stage Sales Sales Titled Lot Lot Club Access Visitors Virtual Tour Open Close

Construction Update

Stage 2 | Stage 2 is Titled                       

Valuations: Any time   |   Estimated Access For Soil Testing: Any time   |   Site Survey: Any time   |   Estimated Title Dates: Titled   |   Settlements Commencement: Any time
Site is open and builds are able to commence. Formal Council PC walkover is booked for 7th December. Streetscape landscaping underway forecast to complete by end of 2023.

100%
Overall Progress
Loading
100%
Phase 1

Planning & Engineering Approvals

Once the Planning Permit has been issued by Council, stage specific plans, including roads and drainage, sewer and water, gas, electrical, telecommunication and landscaping plans, are lodged for approval with the relevant authorities.

100%
Phase 2

Earthworks

Machinery is brought onto site to strip existing topsoil and start shaping the land to ensure that the required levels are met for road and lot construction. This usually includes cutting and filling various areas within the stage, to meet required design levels.

  • Stage 2 Update
Tip: Start your journey with a Villawood Builder Partner and find your future home
100%
Phase 3

Sewerage, Drainage, Water & Gas Reticulation

Trenches are excavated for the installation of underground services, which are usually delivered in order of sewer, drainage, water and gas. The sewerage and drainage network is controlled by gravity, which is why they are often the deepest assets and are delivered first.

100%
Phase 4

Road Base, Kerbs, Electrical & Fibre

Further underground services are installed including electricity and telecommunications (fibre internet). Road construction takes place over several phases. Excavation and preparation of the base layer commences first and is often followed by installation of various conduit crossings and kerb construction.

  • Stage 2 Phase 4
100%
Phase 5

Footpaths, Road Pavement & Asphalting

Construction of the road continues, with numerous road layers completed through to the final asphalt layer. The stage starts to look like your future community, with driveways, footpaths and nature strips created.

  • May Update
100%
Phase 6

Completions & Inspections

Each stage is closely inspected and audited by various authorities to ensure the new infrastructure complies with the plans and relevant standards. The inspections and audits can be quite complex and often take some time to complete. Once all authorities have provided their approvals, Council will issue a Statement of Compliance (SoC).

100%
Phase 7

Titles and Settlements

The construction team are finishing the final verge works. If you are ready to start construction of a home in this stage, please let the sales team know and access can be arranged.

Tip: This is when the land will become available for inspections for valuations and builder assesment
Loading...
Loading...
Loading...
Loading...
Loading...