21% Complete | |
21% Complete | |
21% Complete | |
14% Complete | |
14% Complete |
Stage 1 – October 2026
Stage 2 – October 2026
Stage 3 – October 2026
Stage 4 – Q1 2027
Stage 5 – Q4 2026
Balbethan Drive Overrail Bridge
Pre-works for the bridge commencement have been completed, with final approvals being progressed for construction of the bridge forecast to commence in August.
Raes Road Level Crossing Upgrade
Works have progressed well at the Raes Road rail crossing. This key section, where Raes Road intersects with the existing rail line, has now been significantly upgraded to support the safe movement of heavy construction vehicles. This upgrade is a major milestone, enabling the construction of the western side of the bridge and allowing early civil works to commence on the initial stages of the estate.
Signal Cable Relocation
In preparation for upcoming bridge works, approximately 2.7 kilometres of existing V/Line signalling cables have been successfully relocated. This important milestone ensures the safe continuation of works in and around the rail corridor and marks another step forward in the delivery of key infrastructure for Kimberley.