| 32% Complete | |
| 30% Complete | |
| 29% Complete | |
| 14% Complete | |
| 14% Complete |
Stage 1 – Q1 2027
Stage 2 – Q1 2027
Stage 3 – Q1 2027
Stage 2A – Q2 2027
Stage 5 – Q2 2027
Stage 4 – Q2 2027
Balbethan Drive Overrail Bridge
Construction of the over rail bridge at the end of Balbethan Drive is now underway. Piling and bridge beam installation have been completed, along with the placement of barriers and concrete over the deck. The team is currently progressing well with the construction of wing walls, approach ramps, and associated roadworks.
Raes Road Level Crossing Upgrade
Where Raes Road intersects with the existing rail line, has now been significantly upgraded to support the safe movement of heavy construction vehicles. This upgrade is a major milestone, enabling the construction of the western side of the bridge and allowing early civil works to commence on the initial stages of the estate.
Signal Cable Relocation
In preparation for the bridge works, approximately 2.7 kilometres of existing V/Line signaling cables have been successfully relocated. This important milestone ensures the safe continuation of works in and around the rail corridor and marks another step forward in the delivery of key infrastructure for Kimberley.
In late May we captured some drone footage onsite, which not only shows the works underway, but also captures the breathtaking views and beauty of our community to be, take a look.