Villawood Properties Facebook Facebook Instagram Twitter YouTube Linked In Linked In Email Phone Phone Next Scroll to move Touch to move edit edit Play Play Pause Volume Mute Zoom Search Map Map List Social New Application Document Request User Lot Area Frontage Depth Bedrooms Bathrooms Garage Price Range Download Location Location Filter Bedrooms Bathrooms Bathrooms Lot Size Stage Sales Sales Titled Lot Lot Club Access Visitors Virtual Tour Open Close

Construction Status – July 2025

100% Complete
100% Complete
100% Complete
31% Complete
31% Complete

CONSTRUCTION UPDATE

July 2025

We are pleased to advise that civil construction works for Stages 4 and 5 commenced in May 2025, with internal construction works expected to be completed in November 2025. Sewer works are nearing completion with stormwater now underway.

The next tranche of works to commence include construction of the Mount Lindesay Highway & Eucalee Boulevard signalised intersection and construction of the Sewer Pump Station. Prior to these works commencing, the Telstra, Optus and NBN external services on Mount Lindesay Highway are to be relocated.

The title timing for Stages 4 and 5 is now forecasted to occur as follows:
Stage 4 – Title Registration:  June 2026

Stage 5 – Title Registration:  June 2026

Stage 6 design plans have been approved, with construction of Stages 6 and 7 to follow Stages 4 and 5. We anticipate title timing for Stage 6 as follows:
Stage 6 – Title Registration:  June 2026

We will endeavour to keep you updated as works progress and we receive approvals.

If you have any questions or require further assistance, please don’t hesitate to contact our dedicated sales team at Eucalee Land Sales Office on Ph: 1300 737 598 or eucalee@villawoodproperties.com. We are here to support you every step of the way.

We look forward to welcoming you to the vibrant Eucalee Community.