100% Complete | |
100% Complete | |
67% Complete |
Stage 2
Titles have now arrived for Stage 2!
Stage 3
Titles have now arrived for Stage 3!
Stage 4
Construction is progressing well, with sewer, drainage, road base, and kerb works now complete. Footpaths, road pavement, and asphalting is currently underway. Titles are expected to be issued in April 2025.