Villawood Properties Facebook Facebook Instagram Twitter YouTube Linked In Linked In Email Phone Phone Next Scroll to move Touch to move edit edit Play Play Pause Volume Mute Zoom Search Map Map List Social New Application Document Request User Lot Area Frontage Depth Bedrooms Bathrooms Garage Price Range Download Location Location Filter Bedrooms Bathrooms Bathrooms Lot Size Stage Sales Sales Titled Lot Lot Club Access Visitors Virtual Tour Open Close

Construction Update

Stage 5 | Titles Expected July 2025           

Valuations: Apr 2025   |   Estimated Access For Soil Testing: Jun 2025   |   Site Survey: Jul 2025   |   Estimated Title Dates: Jul 2025   |   Settlements Commencement: Aug 2025

15%
Overall Progress
Loading
75%
Phase 1

Planning & Engineering Approvals

Once the Planning Permit has been issued by Council, stage specific plans, including roads and drainage, sewer and water, gas, electrical, telecommunication and landscaping plans, are lodged for approval with the relevant authorities.

Engineering design continues, with approvals underway. Titles are currently expected to be deposited mid 2025.

30%
Phase 2

Earthworks

The project team is working with the relevant authorities and engineering team in preparation for civil works anticipated to commence in Quarter 2,2025. Titles are currently forecasted to deposit in the second half of 2025.

Tip: Start your journey with a Villawood Builder Partner and find your future home
0%
Phase 3

Sewerage, Drainage & Water Reticulation

Trenches are excavated for the installation of underground services, which are usually delivered in order of sewer, drainage, water, and gas. The sewerage and drainage network is controlled by gravity, which is why they are often the deepest assets and are delivered first.

0%
Phase 4

Road Base, Kerbs, Electrical & Fibre

Further underground services are installed including electricity and telecommunications (fibre internet). Road construction takes place over several phases. Excavation and preparation of the base layer commences first and is often followed by installation of various conduit crossings and kerb construction.

0%
Phase 5

Footpaths, Road Pavement & Asphalting

Construction of the road continues, with numerous road layers completed through to the final asphalt layer. The stage starts to look like your future community, with driveways, footpaths and nature strips created.

0%
Phase 6

Completions & Inspections

Each stage is closely inspected and audited by various authorities to ensure the new infrastructure complies with the plans and relevant standards. The inspections and audits can be quite complex and often take some time to complete. Once all authorities have provided their approvals, Council will issue a Statement of Compliance (SoC).

0%
Phase 7

Titles and Settlements

Lodgement packages are prepared and finalised, individual titles for each lot are issued by the Titles Office. Your solicitor or finance broker is notified when this has occurred and will arrange for settlement.
Once settlement has occurred, your land is ready for you to commence the construction of your new home!