Villawood Properties Facebook Facebook Instagram Twitter YouTube Linked In Linked In Email Phone Phone Next Scroll to move Touch to move edit edit Play Play Pause Volume Mute Zoom Search Map Map List Social New Application Document Request User Lot Area Frontage Depth Bedrooms Bathrooms Garage Price Range Download Location Location Filter Bedrooms Bathrooms Bathrooms Lot Size Stage Sales Sales Titled Lot Lot Club Access Visitors Virtual Tour Open Close

Construction Update

Stage 4 | Titles Expected May 2025           

Valuations: Feb 2025   |   Estimated Access For Soil Testing: May 2025   |   Site Survey: May 2025   |   Estimated Title Dates: May 2025   |   Settlements Commencement: Jun 2025

17%
Overall Progress
Loading
90%
Phase 1

Planning & Engineering Approvals

We continue to work with the Port Adelaide and Enfield Council and our engineering team in finalising the civil design of this stage. With approvals expected soon, this will allow earthworks to commence shortly after. Titles are currently expected to be deposited in mid 2025.

30%
Phase 2

Earthworks

Earthworks are now underway and due for completion in December 2024, ready for the anticipated Stage 4 Civil Works commencement in early 2025. Titles are expected to be deposited mid-2025.

Tip: Start your journey with a Villawood Builder Partner and find your future home
0%
Phase 3

Sewerage, Drainage & Water Reticulation

Trenches are excavated for the installation of underground services, which are usually delivered in order of sewer, drainage, water, and gas. The sewerage and drainage network is controlled by gravity, which is why they are often the deepest assets and are delivered first.

0%
Phase 4

Road Base, Kerbs, Electrical & Fibre

Further underground services are installed including electricity and telecommunications (fibre internet). Road construction takes place over several phases. Excavation and preparation of the base layer commences first and is often followed by installation of various conduit crossings and kerb construction.

0%
Phase 5

Footpaths, Road Pavement & Asphalting

Construction of the road continues, with numerous road layers completed through to the final asphalt layer. The stage starts to look like your future community, with driveways, footpaths and nature strips created.

0%
Phase 6

Completions & Inspections

Each stage is closely inspected and audited by various authorities to ensure the new infrastructure complies with the plans and relevant standards. The inspections and audits can be quite complex and often take some time to complete. Once all authorities have provided their approvals, Council will issue a Statement of Compliance (SoC).

0%
Phase 7

Titles and Settlements

Lodgement packages are prepared and finalised, individual titles for each lot are issued by the Titles Office. Your solicitor or finance broker is notified when this has occurred and will arrange for settlement.
Once settlement has occurred, your land is ready for you to commence the construction of your new home!