Facebook Facebook Instagram Twitter YouTube Linked In Linked In Email Phone Phone Next Scroll to move Touch to move edit edit Play Play Pause Volume Mute Zoom Search Map Map List Social New Application Document Request User Lot Area Frontage Depth Bedrooms Bathrooms Garage Price Range Download Location Location Filter Bedrooms Bathrooms Bathrooms Lot Size Stage Sales Sales Titled Lot Lot Club Access Visitors Virtual Tour Open Close

Construction Update

Stage 11

Winslow Construction have now mobilised on site. Stage 11 site stripping and bulk earthworks are progressing well with drainage and sewer installation to commence early in the New Year.

24%
Overall Progress
Loading
100%
Phase 1

Planning & Engineering Approvals

Engineering plans are with Council for final approval and works are currently being tendered for construction commencement.

70%
Phase 2

Earthworks

Winslow Constructors have now mobilised on site with site stripping and bulk earthworks underway. Sewer and Drainage works are to commence in the coming weeks.

Tip: Start your journey with a Villawood Builder Partner and find your future home
0%
Phase 3

Sewerage, Drainage, Water & Gas Reticulation

Trenches are excavated for the installation of underground services, which are usually delivered in order of sewer, drainage, water and gas. The sewerage and drainage network is controlled by gravity, which is why they are often the deepest assets and are delivered first.

0%
Phase 4

Road Base, Kerbs, Electrical & Fibre

Further underground services are installed including electricity and telecommunications (fibre internet). Road construction takes place over several phases. Excavation and preparation of the base layer commences first and is often followed by installation of various conduit crossings and kerb construction.

0%
Phase 5

Footpaths, Road Pavement & Asphalting

Construction of the road continues, with numerous road layers completed through to the final asphalt layer. The stage starts to look like your future community, with driveways, footpaths and nature strips created.

0%
Phase 6

Completions & Inspections

Each stage is closely inspected and audited by various authorities to ensure the new infrastructure complies with the plans and relevant standards. The inspections and audits can be quite complex and often take some time to complete. Once all authorities have provided their approvals, Council will issue a Statement of Compliance (SoC).

0%
Phase 7

Titles and Settlements

Lodgement packages are prepared and finalised, individual titles for each lot are issued by the Titles Office. Your solicitor or finance broker is notified when this has occurred and will arrange for settlement.
Once settlement has occurred, your land is ready for you to commence the construction of your new home!