Once the Planning Permit has been issued by Council, stage specific plans, including roads and drainage, sewer and water, gas, electrical, telecommunication and landscaping plans, are lodged for approval with the relevant authorities.
The balance of the concreting works are now underway, with only top soiling and lot tidy-ups remaining for completion. Our current program of works for Stage 19 anticipates completion in mid-May 2021, Statement of Compliance in early June 2021, with settlements to follow shortly thereafter in June 2021.